Tanglin Halt Cascadia and Courtyard - August 2026 Update
Tanglin Halt Cascadia
We see really good progress this month, with structural works for both Blocks 74B and 75B nearing completion, pending the roof level. With the first sky terrace floor completed for both 74A and 75A, construction pace for the two 47‑storey blocks continues to move smoothly.
If works maintain this momentum, structural completion for the entire project could realistically come before end‑2027. Structural progress for the residential blocks is currently at ~53% completion with 514 of 973 units completed.
Block 74A: 19 of 47 Floors
Similarly strong progress observed for 75A, advancing from 15-16 floors four weeks ago. As stacks 537/539/541 are 34 floors high, so we may see progress for the block accelerate towards the end.
Block 74A: 25 of 25 Floors
No noticeable change since last month, with structural works pending at the roof level. No rush for this block - Once structural works for the roof are done, installation of roof water tanks, painting and other fixtures and fittings can proceed.
Block 74B: 25 of 25 Floors
Other
Tanglin Halt Courtyard
Block 17A: 19 of 48 Floors
I came across a recent update video by ‘Zai on Site’ on YouTube, which covers progress for both Cascadia and Courtyard quite comprehensively in August.
It’s worth a look, the footage shows strong advancement at the market/hawker centre and the polyclinic, with the facade of the polyclinic being installed! While estimated to TOP 6 months later compared to Cascadia, we may see very similar completion dates given its current progress.