Tanglin Halt Cascadia and Courtyard - August 2026 Update
Tanglin Halt Cascadia We see really good progress this month, with structural works for both Blocks 74B and 75B nearing completion, pending the roof level. With the first sky terrace floor completed for both 74A and 75A, construction pace for the two 47‑storey blocks continues to move smoothly. Tanglin Halt Cascadia taken from Commonwealth 10 on 29 August 2026. If works maintain this momentum, structural completion for the entire project could realistically come before end‑2027. Structural progress for the residential blocks is currently at ~53% completion with 514 of 973 units completed. Block 74A: 19 of 47 Floors From the progress recorded on 1 August (16–17 floors), the latest update implies an advancement of approximately 2.5 floors over four weeks, even with the National Day holiday in between. This is notably faster than the earlier estimate of one floor every two weeks, indicating a clear acceleration in the construction speed. Block 75A: 17-18 of 47 Floors Similarly strong...