Tanglin Halt Cascadia - June 2026 Update

Here is my first update for Courtyard's bigger brother - Tanglin Halt Cascadia! 

Progress has been varied since commencement in early 2024, but we are near the halfway mark with 456 out of 973 units (47%) completed as of 27 June 2026.

The 'Cascadia' is starting to take shape! Taken on 27 June 2026 from Blk 53 of Commonwealth 10.

Block 74A: 15 of 47 Floors

Perhaps due to the greater complexity of building the sky terrace, works on level 15 has been going on since the start of the month. With 74B/75B nearing completion, would we see the progress for 74A/75A quicken? Only time would tell.

Block 74B: 25 of 25 Floors

The end is near! Not much needed to be said.

75A: 14 of 47 Floors

Barely caught up to 74A's progress, but works for the sky terrace at the 15th floor is commencing.

75B: 21-23 of 25 Floors

I've observed stacks 559/561 consistently trailing 563/565 by up to 5 floors since early this year, but at least they are caught up now and are expected to complete in 2 to 3 months.


Others 

There is an early focus on completing the underground works, such as drainage and laying of the pipes for the Pneumatic Waste Conveyance System (PWCS). This is normally done nearer to project completion of other BTO projects.



The carpark was constructed eagerly too. It has been substantially completed since a month ago, pending some items such as the lift shaft and some casting works on the roof garden. At least our cars have a place to stay, for now!


Relocation of some of the internal structures within the construction site as infrastructure works on Commonwealth Drive and the covered drain along the future linear park are expected to commence soon. I will share more details on this in a later post.


That is all for June 2026's construction updates. I am optimistic for key collection by 2028 Q3-Q4.