Tanglin Halt Cascadia - September 2026 Update
Overview
Based on the current pace of construction, both Blocks 74A and 75A appear to be progressing at approximately one floor every two weeks. If this rate is maintained, the majority of structural works could potentially be completed by the end of 2027, with key collection likely taking place sometime in 2028.

Tanglin Halt Cascadia (Left) and Commonwealth 10 (Right) viewed from Commonwealth Dr
Block 74A
Structural works are currently ongoing on the 22nd floor, progressing from the 19th floor reported last month.

Paint was observed on the facade of #06-503, together with the installation of windows. This appears to be a testing or trial installation for the 4 room unit.

Block 75A
Structural works are currently ongoing on the 20th floor, progressing from the 17th-18th floor reported last month.
Blocks 74B and 75B
Others