Tanglin Halt Cascadia - September 2026 Update

Overview

Based on the current pace of construction, both Blocks 74A and 75A appear to be progressing at approximately one floor every two weeks. If this rate is maintained, the majority of structural works could potentially be completed by the end of 2027, with key collection likely taking place sometime in 2028.

Tanglin Halt Cascadia (Left) and Commonwealth 10 (Right) viewed from Commonwealth Dr

Block 74A

Structural works are currently ongoing on the 22nd floor, progressing from the 19th floor reported last month.


Paint was observed on the facade of #06-503, together with the installation of windows. This appears to be a testing or trial installation for the 4 room unit.

Block 75A

Structural works are currently ongoing on the 20th floor, progressing from the 17th-18th floor reported last month.

Blocks 74B and 75B

Not much structural progress has been observed since last month, with the 25th-floor units and roof level still pending completion. It is possible that the precast roof components have yet to arrive, which could explain the pause in structural works. 


Nonetheless, internal works appear to are on-going across the units which have been sealed up with white canvas, and on the lower floors across both blocks, units up to the 7th or 8th floor are observed to have their windows installed.


Others

The car park appears to be nearing completion, with only minor works remaining in various areas. Hoardings are also being gradually removed.


Surface road formation next to the carpark is actively progressing, with the kerb outlines already set out and underground drainage lines visible. 